Overall, the R&D project highlights the potential for successfully mitigating the impact of infrastructure projects through early and enhanced cooperation with pool operators and land agencies, as well as opportunities to optimise the expansion of the electricity grid by consistently harnessing the potential of ecological route management. The recommendations set out here can help to speed up and improve the effectiveness of compensation under the environmental impact compensation scheme, whilst maintaining high quality standards. This involves building on existing approaches and structures to optimise processes quickly and without the need to amend nature conservation legislation.
Müller-Pfannenstiel, K., Pieck, S., Strodick, C. & Lau, M. (2024): Potenziale von Flächen- und Maßnahmenpools sowie des ökologischen Trassenmanagements beim Stromnetzausbau. BfN-Schriften 700