home

EKNA – Environmental impacts of underground cables and options for an environmentally-compatible transmission route design

Project title: Underground cables as an alternative to overhead transmission lines are increasingly under discussion. The project examines the effects of different extra-high voltage underground cable systems on nature and the landscape and provides guidelines on designing underground cable routes in an environmentally sustainable manner.

Focus

  • What are the impacts of an underground cable route on nature and landscape?
  • What usable experiences have been made in practice so far?
  • How can an underground cable route be designed to be environmentally compatible?

Contact

Environmental Action Germany (DUH)
Project management: Dr. Peter Ahmels
Judith Grünert
Hackescher Markt 4
10178 Berlin

Funding

FKZ 3514 82 1600
Departmental Research Plan 2014
Term: 01.12.2014 – 15.04.2016

Underground cables as an alternative to overhead transmission lines are increasingly under discussion. The project examines the effects of different extra-high voltage underground cable systems on nature and the landscape and provides guidelines on designing underground cable routes in an environmentally sustainable manner.

Experience with the construction of extra-high voltage underground cable routes in Germany is still limited. The research project aims to refine the state of knowledge about various extra-high voltage underground cable systems, their determining factors and their impacts on nature and landscape. The state of knowledge was established by evaluating the specialist literature and relevant project documentation from Germany and elsewhere. In addition, experience was evaluated from the construction phase of the extra-high voltage underground cables that have already been laid. The relevance of operational heat emissions for planning and approval was evaluated, based on the results of simulation and test installations. No monitoring has yet been done in actual operation.

The project also looked at the construction of underground cable routes in open ground, woodland and areas close to settlements. Planting underground cable routes with woody species is limited due to safety regulations, which restricts development potential for conservation, particularly for routes across woodland. We therefore investigated the question of what options there might be for a power corridor planted with woody species that was still in line with the technical safety requirements.

Methods

In order to establish the state of knowledge and practice for EHV underground cables, the relevant current scientific literature and planning and approval documentation from completed or currently planned EHV projects in Germany and selected neighbouring countries (NL, DK, BE, GB, CH) were evaluated. The project documentation was assessed in terms of technical requirements and execution, the impacts judged to be relevant and the route design. The evaluation was complemented by interviews and information obtained by telephone or e-mail. Site visits were made to three HVAC projects (Raesfeld, Randstad-Zuidring, Vejle Ådal). This gave rise to a broad knowledge base and a network of contacts in nature conservation.

Issues

Which EHV underground cable projects are currently under construction or planned in Germany and elsewhere and can be used as a reference for the pending EHV underground cable system in Germany?

EHV underground cable projects were identified from an Internet search and by interviewing transmission network operators, and checked in terms of their transferability to the situation in Germany. Project profiles were used to record project data and dimensions, technical design and construction method as well as contacts and project documentation. This also created the basis for a future cross-border knowledge exchange.

Which determining factors and impacts of EHV underground cable projects are potentially relevant for planning and approval and what role do the operational heat emissions play?

The state of knowledge about determining factors and potential impacts was refined on the basis of the technical literature, by evaluating planning and approval documents and from construction reports. One focus was related to the question of what information is available so far on the occurrence of heat emissions and their impacts on the soil (warming), the water regime (drying out) and on soil life, and what relevance is attached to these effects in planning practice. The degree to which practical knowledge from other pipeline projects (natural gas, district heating) can be transferred was also checked.

What options exist for environmentally compatible construction above underground cables? What mitigation or development targets can be developed for the construction design? In which types of landscape is planting woody species preferable from a nature conservation viewpoint?

One focus was on investigating the requirements for the environmentally compatible design with woody species in the case of routes across forests. Various options were developed for an environmentally compatible construction using woody species while maintaining the safety requirements in the buffer strip.

How do the roots of woody species behave and what risk of damage do roots cause? How far can the potential risk of damage be differentiated so that stocking the buffer zone with woody species does not have to be ruled out on principle?

In order to answer these questions, the state of knowledge about the behaviour and depth of the roots of various native species of trees and shrubs was collated. This enabled recommendations for the future use of woody species on cable routes.

Results

The environmental impacts of alternating and direct current projects are essentially the same. Impacts from construction are the main cause of the environmental effects of underground cables. These can be reduced or avoided by an ecological management of the construction. The temperature changes on the surface of the ground due to heat emissions from the cable are within the natural range of variation, according to the current information. As the underground cable technology at the extra-high voltage level is still in the development and test stage, not all the boundary conditions for a final evaluation are currently clear.

Crossing obstacles that cannot be avoided such as streets, running waters or canals can be done by drilling and compacting beneath the obstacle. For longer sections a micro tunnelling process can be considered as a trenchless construction method. These measures can also be used to avoid environmental impacts.

The safety and access requirements of the network operator must be borne in mind when using or planting the route after construction is complete, in particular in the buffer zone (cable trench + safety distances) (no deep-rooting woody species > 1 m root depth). There are fewer restrictions for the rest of the cable route. Native forest trees are therefore not suitable for planting in the buffer zone. The damaging effects of woody species are based mainly on assumptions and conclusion by analogy. There is a need for research in this area in order to confirm or refute these assumptions.

An environmentally compatible construction design can also be achieved even while excluding plants with deep lignifying roots. This requires the establishment of an environmentally compatible route management. The integration of route management in supra-regional interlinked biotope systems only appears to be possible in a few isolated cases.

The environmental impact and the need for an ecological route management are evaluated differently in different European countries. An exchange of views on evaluation criteria and implementation standards would be worthwhile.

Work packages

Work packages

  1. Case study analysis: overview of the HVDC underground cable project and HVDC underground cabling in Germany and selected neighbouring countries (NL, DK, BE, CH, GB); establishing project profiles (including dimensioning, technical execution; studies) as a knowledge base.
  2. Construction, system and operation-related impacts of HVAC and HVAC underground cabling projects; current information / practical knowledge on operational heat emissions; comparability of underground cabling with the range of impacts of natural gas and district heating pipelines
  3. Route design: motives and fundamentals of the obligation to keep the buffer zone open from the operator's viewpoint; options for route design in the buffer zone, emphasis on woodland crossings. Aims of route design: conservation of intact woodland habitats; reduction of fragmentation effect; conservation assessment of the route (including marginal areas); reducing visibility.
  4. Root behaviour of woody species: determination of root depths and root forms of different native woody species; risk of root damage (damage risks); opportunities to reduce risks; classification of woody species by risk damage categories

Project partners

Project partners

Project management

Environmental Action Germany (DUH)
Dr. Peter Ahmels
Judith Grünert; Ole Brandmeyer
Hackescher Markt 4
10178 Berlin

Project partners

Institut für nachhaltige Energie- und Ressourcennutzung (INER)
Hochwildpfad 47
14169 Berlin
Dr. Elke Bruns

Funding authority

Federal Agency for Nature Conservation (BfN)
FG II 4.3 Nature conservation and renewable energies
Alte Messe 6, 04103 Leipzig
Friedhelm Igel
Tel.: +49 341 30977 165
Friedhelm.Igel(at)avoid-unrequested-mailsBfN.de

Print this page

Related News

03.04.2024

Tender published for investigations into floating PV systems

The tender documents were published on the federal procurement platform on 27 March 2024. The submission deadline is 07.05.2024, 12:00h

Weiter

03.04.2024

Nature conservation impacts of floating PV systems

The final report on the first sub-project of a BfN research project on the ecological impact of floating PV systems has been published. However, as the results show, the effects of such systems on nature and the landscape have hardly been researched…

Weiter

15.02.2023

How nature-friendly is the energy transition? "EE-Monitor" gives first answers

Is the number of wind energy and bioenergy plants in protected areas increasing? Are ground-mounted solar plants increasingly being erected on agriculturally valuable land? In a research project funded by the Federal Agency for Nature Conservation,…

Weiter

A man sits in front of a screen showing different aerial photos and maps

Related Projects